Re: [datacenter] peak capacity planning for power vs. cooling



On Wed, 15 Jan 2003, Ofer Inbar wrote:

> Is this a reasonable statement to make:
>
> When planning power capacity for a machine room, you need to base it
> on the peak power consumption of the machines, usually when they are
> powering up / booting, because it is possible that they will all power
> up simulataneously.  However, when planning cooling, you can plan
> based on average load, with some headroom, because even if everything
> will be at peak heat output simultaneously, it will be a brief event,
> and cooling averages out naturally over time.


For technical purposes, I'd say plan is based on the watts-per-square-foot
number.



---------------------------------------------------------------------